Historic Courthouse Square Project April Update
- Monday 3/29 Stage Waterproofing and Touch Up Framing
- Tuesday 3/30 Union Street Electric and Water lines finished up
- Wednesday 3/31 Framing and Carpentry work on columns adjusted.
- Thursday 4/1 Rainfall
- Friday Wet site, rock masons continued to lay new rockwork, Door hardware installed.
- Monday 4/5 Top Stage Pour complete and Sawed
- Tuesday 4/6 Roof Leaders and Trench Drain lay out work.
- Tuesday through Wednesday Electrical and Plumbing work.
- Friday 4/9 Plumbing insulated.
Rain events have slowed down and we have had remarkable working conditions including cool mornings and warm afternoons after what we hope is the last cold spell. Check out some progress photos of the project below.